P-04 · Villa

6th of October villa

A two-storey villa with a roof, a double-height reception, a marble stair and simple landscaping.

Location
October Gardens
Area
340 m²
Duration
22 weeks
Level
Luxury
The October villa entrance and stair after finishing, from the same angleThe October villa entrance and stair before finishing: bare plaster and concrete floor
Drag the line or use the arrow keys to compare.

Scope of work

  • Full interior finishing on both floors
  • Paint and stone facade
  • Lit double-height ceiling
  • Central AC ducting

Materials

  • Egyptian marble for stair and reception
  • Beech doors
  • UV-resistant exterior paint

Stages

The actual schedule in weeks (22 weeks). Some stages overlap because crews work in parallel.

  1. Groundwork, both floorsWeek 1–5
  2. Central ACWeek 4–7
  3. Marble and floorsWeek 7–12
  4. Gypsum and lightingWeek 11–16
  5. Facade and paintWeek 15–20
  6. HandoverWeek 20–22